Contractor job costing
What’s left in this job’s budget?
A job can look comfortably under budget while a single cost code is already over. See which costs have posted, which orders are still open and which lines your project manager should check.
Fictional job · Worked example
One job at cutoff
| Approved budget | $23,000 |
|---|---|
| Costs already posted | $14,085 |
| Open, uninvoiced orders | $4,930 |
| Posted plus open | $19,015 |
| Budget remaining | $3,985 |
Check electrical materials. That code is already $240 over budget. Confirm the open order balance before approving another materials purchase.
Future labor and purchases can still change the result.
Fixed-scope service
One job. One cutoff date.
$595 one time
What we use
Your agreed budget by cost code, posted costs through a common date, and the remaining uninvoiced balance of each open order. The pilot covers up to 12 cost codes and 100 transaction lines in spreadsheet or CSV exports, with one currency.
What you receive
An editable Excel workbook comparing each code with its budget, a check against your export totals and a list of missing or conflicting entries for your office to resolve. A 20-minute walkthrough and one correction round are included.
How to start
Tell us which reports you can export and their approximate size. Keep customer and employee details out of the inquiry. We confirm fit, secure transfer, dates and written terms before starting. Allow two business days after the agreed start and receipt of complete usable exports.
We work from copies. Your team controls any accounting entries, purchasing decisions or changes to the source systems.
Request a scope check →